Math, asked by neelammishra3891, 10 months ago

A contractor who had a work force of 630 persons, to complete a portion of a stadium in 14 months. he was asked to complete the job in 9 months. how many extra persons had he to employ? ​

Answers

Answered by Love22036
5

= 630*9/14

=45*9

=405 Ans