a contractor who had a workforce of 294 undertook to complete a work in 9 days due to emergency he was asked to complete the job in 7 days how many extra man should he employ to complete the work in time
Answers
Answered by
1
Answer:
294 × 9 = x × 7
x = 294 × 9/7
x = 378
therefore, extra men needed = 378 - 294 = 84