a contractor who had a workforce of 630 people undertook to complete a portion of stadium in 14 months he was asked to complete the job in 9 months how many extra persons have to be employ​

Answers

Answered by manoj8753
9

According to me

people months

630 14

x 9

cross multiply

14x=630×9

x=630×9/14

X=405

so, they need 405 more employees to complete the part of stadium in 9 months

if the answer is correct please mark it as brainliest


smileypriya: not correct