Math, asked by jinadevkv, 11 months ago

A contractor wishes to determine a suitable combination of manual labour and machine work for the excavation of a multistory construction. For every cubic meter of excavation, 3 man-hours are needed; or 0.2 machine-hour. Costs involved are Rs. 20 per man-hour and Rs. 500 per machine-hour. The total quantity of excavation is estimated to be 4,000 cubic meter. The optimal quantity of excavation to be done manually for minimum total cost will be

Answers

Answered by Gaurav005
0

Answer:

The total machine-hour is 200 and the total cost is Rs. 100000 and the total man-hour is 1333.33......

Answered by amitnrw
0

We need more constraints to find optimal quantity of excavation to be done manually for minimum total cost

Step-by-step explanation:

For every cubic meter of excavation, 3 man-hours are needed

Costs involved are Rs. 20 per man-hour

=> Cost for every cubic meter of excavation manually  = 3 * 20 = Rs 60

For every cubic meter of excavation,  0.2 machine-hour are needed

Costs involved are  Rs. 500 per machine-hour.

=> Cost for every cubic meter of excavation machine = 0.2 * 500 = Rs 100

The total quantity of excavation is estimated to be 4,000 cubic meter.

We need more constraints to find optimal quantity of excavation to be done manually for minimum total cost

otherwise 100 % work will be done manually  as Cost for every cubic meter of excavation manually is less than by machine

Constraints Can be available Man , available machines , number of days  work to be finished

Learn more:

solved by simplex method- Max Z= 3x1+2x2 s.t. 5x1+x2≤10 4x1+ ...

https://brainly.in/question/8809746

Minimize and maximize z=3x+9y subject to x+3y≤60, x+y≥10, x≥y ...

https://brainly.in/question/11773733

Similar questions