A contractor with a work force of 420 men can complete construction of a building in 9 months. Due to request by the owner he was asked to complete the job in 7 months. How many extra men he must employ to complete the job?
Answers
Answered by
1
Answer:
120
Step-by-step explanation:
No of works -420
No of days they take to complete work=270
No of days work needs to be done by=210
No of works to do work in 210 day= 220*270/210=540
No of extra workers required=540-420=120
Answered by
2
Answer:
Step-by-step explanation:
Let work to be done be x
Time taken by 420 persons to complete the work. x= 9 months
x= 420×9 = 3780
People required to complete the work in 9 months= x÷7= 3780÷ 7
3780÷7 = 540
Therefore, the contractor had to employ 540 people more to complete the job.
☆ HOPE IT HELPS YOU☆
Similar questions
Physics,
15 days ago
Math,
15 days ago
English,
15 days ago
Computer Science,
1 month ago
Math,
9 months ago
Environmental Sciences,
9 months ago
CBSE BOARD X,
9 months ago