A contractor with a work force of 420 men can complete a work of construction of a building in nine months. Due to request by the owners he was asked to complete the job in seven months. How many extra men he must employ to complete the job?
rumamukherjee4166:
give the answer fast friend i will follow you and you will follow me
Answers
Answered by
10
required answer = 540 men
Answered by
28
Hope this helps.
Pls follow me and mark this answer as brainliest.