A contractor with a work force of 420 men can complete a work of construction of
a building in nine months. Due to request by the owners he was asked to complete
the job in seven months. How many extra men he must employ to complete the job?
Answers
Answer:
Let a be the extra number of men employed to complete the work in 7 months.
Number of men 420 a
↓ ↓
Months 9 7
As we know,
the number of men hired and the time required to finish the piece of work are inversely proportional.
Therefore,
420 × 9 = a × 7
a = 540
The number of extra men required to complete the job in 7 months
= 540 - 420 = 120
Answer: 120
Step-by-step explanation:
Assumption :-
Work to be done be p
Also,
420 persons to complete the work time taken :-
p = 9 months
Hence,
p = 420 × 9
p = 3780
Now,
Complete the work in 9 months
p = 540
People Required :-
= 540 - 420
= 120
Hence we get,
Contractor had to employ 120 people more
Additional Information :-
→ If a person Q completes 1/c th part of work in one day, then the time taken by Q to complete the work = c days
→ If a man takes 50 days to complete a piece of work then according to the unitary method work done in a 1 day = 1/50