A contractor with a work force of 420 men can complete a work of construction of a building in nine months . due to request of owners he was asked to complete the job in seven months . how many extra men he must employ to complete the job
Answers
Answered by
0
Answer:
lemma marks sleeve Melissa all Bella
Answered by
0
Answer:
60
Explanation: