a contractor with a work force of 420 men who can finish a certain piece of work in 9 months . how many extra men must be employ to complete the same job in 7 months .
Answers
Answered by
7
please mark my answer as brainliest
Step-by-step explanation:
Men Time
420 9 months
x 7 months
As the number of workers is inversely proportional to time taken:
420×9=x×7⟹x=
7
420×9
=540
∴ extra men needed: 540−420=120