Math, asked by journeyburke9376, 9 months ago

a contractor with the workforce of 4 20 men can complete a work of construction of a building in 9 months due to request by the owner he was asked to complete the job in 7 months how many extra man he must employee to complete the job

Answers

Answered by haridasan85
1

Answer:

men. Time

420. ... 9 mos

x. ? .. 7mos

Step-by-step explanation:

x=Totalmen

x = 9x420/7=540

extra men required=540-420=120