A do a work in 5 days.B do in 3 days. With the help of c do in 4 days

Answers

Answered by ram071987
2
A does in 5 days
A's 1 day work = 1/5
B does in 3 days
B's 1 day work = 1/3
C does in 4 days
C's 1 day work = 1/4
(A+B+C)'s 1 day work =
( \frac{1}{5}  +  \frac{1}{3}  +  \frac{1}{4} ) \\  =  \frac{12 + 20 + 15}{60}  \\  \frac{47}{60}
time taken to complete the same work = 1/1days work
 =  \frac{1}{ \frac{47}{60} }  =  \frac{1}{1}  \times  \frac{60}{47}  \\  =  \frac{60}{47}  = 1 \frac{13}{47} days