A does 1/2 as much work as B and C does1/2as much work as A and B together. If C alone can finish the work in 40 days, then together all will finish the work in
A) 30 days B) 40/3 days C) 15 days D) 16 days
Answers
Answered by
0
Answer:
40/3 days is answer this question
Answered by
0
Step-by-step explanation:
C's work of 1 day =1/40
(a+b) work of 1day,=1/20
so, 1 day work of a, b & c
1/40+1/20 = 1+2/40=3/40
required time
40/3 or 13 1/3 or13.33
hope you will like this