Math, asked by surbhi089, 3 months ago

A Does 30% of a work in 30

days. He then calls in B and they

together finish the remaining work

in

20 days. How long B alone would

take to do the whole work? ​

Answers

Answered by raviyadav90
0

Answer:

good

Step-by-step explanation:

left work =70%

remain work done by both =20 days

it means b alone done = 50 daus