Math, asked by jayakrishna1451, 9 months ago

A does 4/5 of a work in 20 days. he then calls in b and they together finish the remaining work in 3 days .how long b alone would take to do the whole work? select one: a. 23 days b. 37 days c. 37 days d. 40 days

Answers

Answered by hraja8066gmailcom
3

Answer:

last part

b one day work =2/75

therefore b can complete the work in 75/2= 37.5 days

Step-by-step explanation:

37.5days