A does 50% of a work in 12 days. He then calls in B and they together finish the remaining work in 8 days. How long B alone would take to complete the whole work?
A) 12 days B) 24 days C) 36 days D) 48 days
Answers
Answered by
0
Answer:
The answer is a option B