Math, asked by mounikaarun13, 6 months ago

A does 7/10 of a piece of work in 15 days. He does the
remainder with the assistance of B in 4 days. In what
time could A and B together do it?
days​

Answers

Answered by tanujagautam107
0

A completes 7/10 of the work in 15 days

Remaining work = 1 - 7/10 = 3/10

A+B take 4 days to complete the remaining work, 3/10 of the work

So, for the entire work, A+B will take 4 * (10/3) days

=40/3 days = 13.33 Days