A does 8/15 of a work in 8 days and the remaining work is finished with assistance of B in 4days.How long will B take to do the work alone?
Ramcharan:
wait
Answers
Answered by
0
balance work =7/15
to do full work= 4*15/7=60/7.
to do full work= 4*15/7=60/7.