A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?
A) 12.5 days B) 100 days C) 22.5 days D) 35 days
Answers
Answered by
0
C is the answer mate......
Similar questions
Social Sciences,
4 months ago
Hindi,
4 months ago
Hindi,
4 months ago
Math,
8 months ago
Math,
8 months ago
Chemistry,
11 months ago
Math,
11 months ago
Social Sciences,
11 months ago