A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?

A) 12.5 days B) 100 days C) 22.5 days D) 35 days

Answers

Answered by Anonymous
0

C is the answer mate......