A does 80% of work in 20 days , he then calls b and they together finish remaining work in 3 days how long b alone can do the work
Answers
Answered by
0
Answer:
75/2 days
Step-by-step explanation:
A does 80% of work in 20 days
A can do 100% work in 25 days
Consider Total work = 1
Then A can do 1/25 th of work in 1 day.
80 % of work of work is completed by A in 20 days. 4/5 th of work is completed.
A and B can do remaining 1/5 th of work in 3 days
b can do a work in 75 / 2 days .