A does a work in 10 days and B does the work in 15 days . In how many days will they together do the same work ?

Answers

Answered by vijaykumar15
1
7.5 days if not A and B work together.
Answered by tanya2601
6
Work done by A = 1/10

Work done by B = 1/15

therefore,
total work done = 1/10 + 1/15
= (3 + 2)/30
= 5/30
=1/6
So, they will together do the same work in 6 days..