Math, asked by gurbakshsingh5161, 1 year ago

A does four fifth of a work in 20 days he then calls in b and they work together finish the remaining work in 3 days how long be alone would take to do the whole work

Answers

Answered by Supraptilove
0
A can do 4/5th works in 20 days.
so he can do the whole work in 20*(5/4) =25 days.
remaining work after done 4/5 by A is=1-(4/5)=1/5
(A+B) can do the 1/5th work in 3 days.
means the can do the whole work in (3*5)=15 days.
so,(A+B)'s 1 days work=1/15
B's 1 day's work {(1/15)-(1/25)}=2/75
so B can alone do the whole work in 75/2,means in 37 1/2 days.