A ek kaam ko 20 din me ,B 30 din me tatha C 60 din me kar skta hai ydi A ko har ek tisare din B or C se madat mile to kaam kitane jaldi samapt ho jayega
Answers
Answered by
1
Answer:
Can you write in English please!!
Answered by
0
Answer:
15days
Step-by-step explanation:
work done by A in one day is (1/20) of total work...
similarly ,
workdone by B in one day is (1/30)
and of C is (1/60)
let us calculate how much work is done in 3days
3*(1/20) + (1/30) + (1/60) = (1/5)
there fore in every 3days one fifth work is completed so we need to repeat this 5 times to complete the work
there fore number of days taken will be 5*3 = 15 days