a ek kaam ko Das dino me karta hai a aur b mil kar Usi kam ko 6 Dino Mein Karte To B Akela us kaam ko kitne din Mein pura Karega
Answers
Answered by
4
a - 10 b -? a+b -6 3 --A--10 TOTAL WORK 30 (LCM) ?--B--? _______ 5--a+b--6 B KA ONE DAY WORK AAYEGA --2 THN B' S WORK -- 30/2 =15
Answered by
0
15 days mai because A=10days and A or B 6days 6/2=3, and total work is 30 and B complete the work 30/2=15days