Math, asked by zakhiyajumana08, 11 months ago

A factory can produce 60 TV in 7 days ? How long does it take to finish 400 TV ? please explain it in detail....

Answers

Answered by Asterinn
4

Answer:

47

Step-by-step explanation:

Given : factory can produce 60 TV in 7 days

To find : time to finish 400TVs

Solution :

Number of days taken to produce 60Tvs = 7

Number of days taken to produce 1 Tv = 7/60

Number of days taken to produce 400Tvs = 7/60× 400

= 2800/60

= 280/6 = 46.66

= 47 days approximately

mark my answer as brainliest please ♥️

Answered by Anonymous1215
1

46 days 6 hours is the answer