Math, asked by sudhiragarwal129, 5 months ago

A factory has 225 labourers who take care 72 days to complete the planned production . If the production has to be completed in 90 days , how many labourers will be required ? Please answer the question , also I want correct answer​

Answers

Answered by AnythingAA
1

Answer:

270 labourers

Step-by-step explanation:

72 days=225 labourers

1 day=225/72

1 day=3 labourers

90 days=3*90

90days=270

Answered by shravyad2009
1

Answer:54

Step-by-step explanation:because first we need to see how many labourers will be required to do one days production so we need to do 225÷72 then we get answer as 3 .now we have to remove days of which we have to exceed days that is 90-72=18 so to find the lauberers just multiply 18×3=54

i hope you got your answer.please follow mw to get like this more explanations