A father can do a job twice as fast as his two sons combined. If his one son can do a job in 3 hours and other in 6 hours. How much time will the father take to complete the job?
Answers
Answered by
3
Answer:
Work done by Son1 in one day=1/24
Work done by Son2 in one day=1/40
Work done by both in one day=1/24+1/40 =8/120 = 1/15
Therefore, Time takby both sons to complete work=Time taken by father to complete work=15
Hope this helps....
Please mark a Brainliest
Step-by-step explanation:
Similar questions