A feild can be cleared by 33 men in 15days. How many more men will be required if the feild has to be cleared 4 days earlier.

Answers

Answered by RajMishraBrilliant
0

Answer:

Follow me

Answer=40 men

Answered by absara143
4

Answer:

No. of men required to clean the field in 15 = 33

No. of men required to clean the field in 1 day = 33×15

So, no. of men required to clean the field in 4 days earlier than 15 days i.e. 11 days = 33×15/11

= 3×15

= 45

hope it helps buddy please mark as the brainliest answer and do follow me.....