A finish the work in 10 days,b finish it in 15 days. A work for 5 days and then b join,in how many days one can finish the work
Answers
Answered by
0
A finishes the work in 10 days. B finishes the same work in 15 days. Together they can finish in how many days?
Still have a question? Ask your own!
What is your question?
Ad by Mailchimp
Keep your business growing.
We make it easy to find your people with social ads, postcards, landing pages, and more.
Learn More
73 ANSWERS

Sanghamitra Barve
Answered Mar 2, 2017
Explanations :- A's 1 day work = 1/10
B’s 1 day work = 1/15
So taken together A and B, both of them complete work in 1 day.
(A + B)'s 1 day work = 1/10 +1/15
= 3+2/30 ( take the l.c.m of 10 & 15)
=5/30
=1/6
So, Number of days they take to finish work together = 1/6 = 6 days
1//1
Still have a question? Ask your own!
What is your question?
Ad by Mailchimp
Keep your business growing.
We make it easy to find your people with social ads, postcards, landing pages, and more.
Learn More
73 ANSWERS

Sanghamitra Barve
Answered Mar 2, 2017
Explanations :- A's 1 day work = 1/10
B’s 1 day work = 1/15
So taken together A and B, both of them complete work in 1 day.
(A + B)'s 1 day work = 1/10 +1/15
= 3+2/30 ( take the l.c.m of 10 & 15)
=5/30
=1/6
So, Number of days they take to finish work together = 1/6 = 6 days