A finishes a task in 15 days. but with the help of b he finishes the same work in 12 days.how much time b alone will take to finish the work

Answers

Answered by kk123456789kk
1
Work done by A =1/15
Work done by A and B =1/12
Work done by B =1/12-1/15=1/60
Work done by B =60