“A” finishes his work in 15 days while “B” takes 10 days. How many days will the same
work be done if they work together? get
Answers
Answered by
12
Given :-
- A can do a piece of work in 15 days
- B can do the work in 10 days
Aim :-
- To find the total number of days taken to complete the work when A and B both work together
If B can do the work in 10 days, then in one day B, can do :-
th part of the work.
If A can do a piece of work in 15 days, then in one day A did :-
th part of the work.
Therefore, for 1 day, if they work together, then work done will be :-
Taking LCM = 30,
Putting the values in the equation,
Adding,
Reducing to the lowest terms, (dividing the numerator and the denominator by 5)
This is the work done in 1 day. Therefore the total number of days taken to finish the work :-
Hence, if A and B both work together, then the work can be done in 6 days
Answered by
2
Answer:
Your correct answer is...
Step-by-step explanation:
6 Days...
Please mark me as Brainliest...
Similar questions