Answered by ganiskaur
1

Answer:

2nd option is the correct answer

i hope u like my answer

mark me as brainliest

Answered by Anonymous
0

Given: The mass of the object =2kg

The speed of the object of the given mass from rest is =10m/s

To find: The work done in the process.

Solution:

Mass of the object given = 2kg

The speed of the object of the given mass from rest is =10m/s

As the mass and velocity are given and it is said that the force changes the speed from rest, this means that the object has acquired kinetic energy.

In this case, the work done will be the total kinetic energy of the object.

The kinetic energy for a body is given by,

K.E =\frac{1}{2}mv^2

⇒ K.E =\frac{1}{2}*2*10*10

⇒ K.E =100J

∴The work done in this process = Kinetic Energy of the body =100J

Final answer:

The correct option is option(3)100J