a group of labourers promise to do a piece of work in 10 days but five of them become absent if the remaining labours complete the work in 12 days find the original number in the group?
Please answer
Answers
Answered by
3
Answer:
CASE 1:
as 12 men will do the work in -18 days.
so 1 man do the work in -12*8 days
CASE2:
15 is correct. Let W be the work. x be the original number of men.
eqn 1. W=12x
eqn 2. W=18(x-5)
Thus 12x=18x-90
Solving we get x=15
1 day work for x men=1/12*x
1 day work for x-5 men=1/18(x-5)
1/12*x=1/18(x-5)=15