A group of labourers promised to do a piece of work in 10 days, but five of them become absent. If the remaining labourers complete the work in 12 days, find their original number in the group
Answers
Answered by
13
Answer:
Total period = 10 days
But work completed in = 12 days
No. of men were absent = 5
Let the number of men in the beginning = x
Now x men can do a piece work in = 10 days
1 man will do it in = 10x x days
And (x – 5) will do it in = (10 × x)/(x – 5) days
∴ 10x/(x – 5) = 12 ⇒ 10x = 12x – 60
⇒ 12x – 10x = 60 ⇒ 2x = 60
⇒ x = 60/2 = 30
∴ No. of men in the beginning = 30
Answered by
5
Step-by-step explanation:
Let the number of labour =x
Initially work should be completed in 10 days
so for one labour it takes 10×x days
But when the labour is 5 less it will complete in 12 days
so for one labour it takes 12×(x−5) Days
hence 10x=12×(x−5)
⟹10x=12x−60
⟹10x−12x=−60
⟹−2x=−60
⟹x=30
Hence in starting number of labour =30.
Similar questions