Math, asked by NANIPARUPALLI1998, 2 months ago

A group of students volunteered to finish a construction work in 25 days. 1Q of the students did not come and the

work could be finished in 35 days. The original number of students in the group were​

Answers

Answered by itzdreamer44
0

Men Days

x 25

x-10 35

x/x - 10 = 35/25

x/x - 10 = 7/5

7x - 70 = 5x

2x = 70

x = 35