A group of workers needed to mow two lawns. The area of the first lawn is two times greater than the area of the second lawn. On the first day, all workers were mowing the first lawn. On the second day, half of the workers continued to mow the first lawn, and the other half of the workers started mowing the second lawn. At the end of the second day, the first lawn was mowed but one worker needed to mow 2 more days to finish the second lawn. How many workers were in the group?
Answers
Answered by
4
Answered by
1
Step-by-step explanation:
A group of worker needed to mow 2 lawns.the area of the 1st lawns is two times greater than area of the second lawn.on the first day,all workers were mowing the 1st lawn.on the second day ,half of the workers continued to mow the 1st law and the other fay half of the workers started moving the second lawn .at the end of the second day the first lawn was mowed but one worker needed to mow 2 more days yo finished the second lawn..how mamy workers were in the group??