A hotel has requested a manufacturer to produce pillows and blankets for their room service. For materials, the manufacturer has 750 m² of cotton textile and 1,000 m² of silk. Every pillow needs 2 m² of cotton and 1 m² of silk. Every blanket needs 2—1.5 m² of cotton and 5--1 m² of silk. The price of the pillow is fixed at $5---50 and the blanket is fixed at $10--40. What is the number of pillows and blankets that the manufacturer must give to the hotel so that these items obtain a maximum sale? Formulate the problem using mathematical modelling of LPP and define the objective function?

Answers

Answered by amitnrw
3

Given : the manufacturer has 750 m- of cotton textile and 1,000 m- of silk. Every pillow needs 2 m2 of cotton and 1 m of silk. Every blanket need 2 mº of cotton and 5 m2 of silk. The price of the pillow is fixed at $5 and the blanket is fixed at $10.

To find : LPP

Solution:

Pillow P

Blanket  B

2P + 2B ≤ 750

=> P + B ≤ 375

   P  + 5B   ≤ 1000

Cost =  5P  + 10B  

 

Learn More:

Shalmali wants to invest ₹50,000 in saving certificates and PPF ...

brainly.in/question/6332423

solved by simplex method- Max Z= 3x1+2x2 s.t. 5x1+x2≤10 4x1+ ...

brainly.in/question/8809746

Similar questions