‘A’is 40% less efficient than ‘B'who can do the same work in 20% less time than 'C'. IfA and B togethe
can complete 80% of work in 12 days, then in how many days 60% of work can be completed by B and C together.
1.2 days
2. 4 days
3. 6 days
4.8 days
5.10 days
Answers
Answer:
70 days
Step-by-step explanation:
Let C's efficiency be 100, B's will be 80 and A's 112. Reducing we get the ratios as 28:20:25
No.of days required for work ( inversely proportional) LCM =700
Days: A:B:C = 25 : 35: 28
When difference of days between A and C is 3 , C takes 28 days. Hence when actual difference is 6 days C will take 6*28/3 = 56 days. Therefore A will take 50 days.
B is 40% less efficient than A and hence takes 50*35/25 = 70 days.
Concept :
Efficiency is the proportion of user-inputted work (input work) that is converted into output work by a machine (output work). Because some of the attempt to evaluate is needed to remove friction, the return work is always lesser than the input work. As a result, efficiency is never percent.
Given:
A’is % less efficient than ‘B'who can do the same work in % less time than 'C'. If A and B together can complete 80% of work in days
Find:
how many days 60% of work can be completed by B and C together.
Solution:
According to the problem,
Let C's efficiency be , B's will be and A's . Reducing we get the ratios as
No.of days required for work ( inversely proportional) LCM =
Days: A:B:C =
When difference of days between A and C is , C takes days. Hence when actual difference is days C will take days. Therefore A will take days.
B is 40% less efficient than A and hence takes days.
Hence the answer is days
#SPJ2