Math, asked by gannag85, 3 months ago

‘A’is 40% less efficient than ‘B'who can do the same work in 20% less time than 'C'. IfA and B togethe
can complete 80% of work in 12 days, then in how many days 60% of work can be completed by B and C together.
1.2 days
2. 4 days
3. 6 days
4.8 days
5.10 days​

Answers

Answered by sanjanapalvankar2
8

Answer:

70 days

Step-by-step explanation:

Let C's efficiency be 100, B's will be 80 and A's 112. Reducing we get the ratios as 28:20:25

No.of days required for work ( inversely proportional) LCM =700

Days: A:B:C = 25 : 35: 28

When difference of days between A and C is 3 , C takes 28 days. Hence when actual difference is 6 days C will take 6*28/3 = 56 days. Therefore A will take 50 days.

B is 40% less efficient than A and hence takes 50*35/25 = 70 days.

Answered by setukumar345
0

Concept :

Efficiency is the proportion of user-inputted work (input work) that is converted into output work by a machine (output work). Because some of the attempt to evaluate is needed to remove friction, the return work is always lesser than the input work. As a result, efficiency is never 100 percent.

Given:

A’is 40% less efficient than ‘B'who can do the same work in 20% less time than 'C'. If A and B together can complete 80% of work in 12 days

Find:

how many days 60% of work can be completed by B and C together.

Solution:

According to the problem,

Let C's efficiency be 100, B's will be 80 and A's 112. Reducing we get the ratios as 28:20:25

No.of days required for work ( inversely proportional) LCM =700

Days: A:B:C = 25 : 35: 28

When difference of days between A and C is 3 , C takes 28 days. Hence when actual difference is 6 days C will take 6*28/3 = 56 days. Therefore A will take 50 days.

B is 40% less efficient than A and hence takes 50*35/25 = 70 days.

Hence the answer is 70 days

#SPJ2

Similar questions