Math, asked by althafa3002, 9 months ago

A is 50% more efficient than B. They together start the work and 7/12th of work is left after 8 days. Find in what time B alone will complete the whole work.
A) 36 days B) 44 days C) 50 days D) 40 days

Answers

Answered by SwaggerGabru
1

QUESTION -

A is 50% more efficient than B. They together start the work and 7/12th of work is left after 8 days. Find in what time B alone will complete the whole work.

ANSWER -

Ratio of efficiency of A to B is 3 : 2

Let, In 8 days they complete = (3 + 2) × 8 = 40 units

So, total work = 40 × 12/5 units

Time taken by B alone to complete whole work = 40 × 12/5 ×2 = 48 days

(answer)

Answered by abcdefghi76
0

Answer:

48 is answer of question