A is 60% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 28 days?
A) 20 days
B) 23 days
C) 17313 days
D) 26 days
E) None of these
Answers
efficiency and time are inverse
A is 60% faster than B
160:100 is x X 28
B work efficiency is 224/5
A 1 day work =1/28
B. 1 day work is 5/224
add both to get A+B as 17 3/13. which is C
Answer:
option C
Step-by-step explanation:
A is 60% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 28 days?
A) 20 days
B) 23 days
C) 17313 days
D) 26 days
E) None of these
A alone could do in 28 days
A's 1 day work = 1/28
Let say B's 1 day work = B
A is 60% more efficient than B
so A's 1 day Work = B's 1 day work + 60% of B's 1 day work
1/28 = B + (60/100)B
=> 1/28 = 8/5B
=> B = 5/(28 * 8)
=> B = 5/224
A + B together 1 day work = 1/28 + 5/224
= (8 + 5)/224
= 13/224
Time taken to complete job = 1/(13/224) = 224/13
=
option C