A is four times as fastern as B and therefore able to finish a work in 60 days less than B. Find the time in which they can finish the work if they work together?​

Answers

Answered by NikitaDutta2007
2

REQUIRED ANSWER ✍️:-

22.5 DAYS

SOLUTION ☄️:-

The efficient ratio of A to B is 3:1.

Therefore the time ratio is 1:3.

The difference in the ratio is 2, that corresponds to 60 days.

Hence A takes 30 days and B takes 90 days.

If they work together, they take

3×90/30+90

=90/4

= 22.5 days.