A is three times more efficient worker than B and is therefire able to complete a work in 60 days less than B. What is the number of days that A and B together will take to complete the work ?
Answers
Let B take b days to complete a job. So A takes (b-60) days to complete the same job.
B does (1/b)th part of the work in a day, while A does (3/b)th part of the work in a day.
So we have A doing [1/(b-60)]th or (3/b)th part of the work in a day.
So equation the two we get [1/(b-60)] = (3/b), or
b = 3b - 180, or
180 = 2b, or b = 90 days. So A takes 90–60 = 30 days.
A does (1/30)th part of the work in a day while B does (1/90)th part of the work in a day. A and B together will do (1/30)+(1/90) = (3/90)+(1/90) = 4/90)th part of the work in a day.
So A and B will complete the work in 22.5 days, working together.
Answer:
Let B complete the work in x days. Then,
A will complete the same work in x/3 days.
Given, x – x/3 = 60
=> 2x/3 = 60
=> x = 60 × 3/2 = 90 days.
Therefore A will complete the work in 30 days.
(A + B)'s 1 days' work
= 1/90 + 1/30
= 4/90
=> (A + B) will complete the whole work in 90/4
= 22.5 days.