A is three times more efficient worker than B and is therefire able to complete a work in 60 days less than B. What is the number of days that A and B together will take to complete the work ?
Answers
Answered by
1
Step-by-step explanation:
The efficient ratio of A to B is 3:1. Therefore the time ratio is 1:3.
The difference in the ratio is 2, that corresponds to 60 days.
Hence A takes 30 days and B takes 90 days.
If they work together, they take 30*90/30+90 = 90/4 = 22.5 days.
Answered by
1
Answer:
Let B complete the work in x days. Then,
A will complete the same work in x/3 days.
Given, x – x/3 = 60
=> 2x/3 = 60
=> x = 60 × 3/2 = 90 days.
Therefore A will complete the work in 30 days.
(A + B)'s 1 days' work
= 1/90 + 1/30
= 4/90
=> (A + B) will complete the whole work in 90/4
= 22.5 days.
Similar questions