Math, asked by brajmohanprajapatiap, 7 days ago

A is thrice as efficient as B and hence completes a work in 40 days less than the number of days taken by B. What will be the number of days taken by both of them when working together?​

Answers

Answered by jeetchourasia7
0

Answer:

15 days

Step-by-step explanation:

Since A is three times more efficient than B, if A completes a work in x days, then B can complete the same work in 3x days.

It is also given that A can complete a work in 40 days less time than B, that is,

3x−x=40

⇒2x=40

⇒x= 40/2

⇒x=20

And, 3x= 3×20 =60

This means that when B can complete the work in 60 days, A can complete it in 20 days. So, both can together finish the work in:

20×60

---------

20+60

= 1200/80

=15 days.

Hence, both A and B can complete the work in 15 days.