Math, asked by tusharbaliyan2141, 1 year ago

A is twice as good as workman b and together they finish a piece of work in 14 days the number of days taken by a alone to finish work is in how many days

Answers

Answered by inhumandrowsey
43

Let B finishes work in = x days


A will finish the work in = x/2 days


1 day of work done by both together is


2/x + 1/x = 1/14


3/x = 1/14


x = 42


So B will complete work in 42 days

And A will complete in 21 days


Answered by 9177616455
6

Answer:

Step-by-step explanation:

Attachments: