a job can be completed in 12 days by one man or two women in how many days can one women and one man complete the same job.​

Answers

Answered by ssmishramart
1

Step-by-step explanation:

one man can complete a job in = 12 days

one man can complete same job in = 12 days

two women can complete a job in = 12 days

one woman can complete same job in= 12 ÷ 2

= 6days