A job is completed in 10 days if 16 women work on it. if it's required to complete the job in a span of 40 days. how many women can be assigned?
Answers
Answered by
0
10days if 16 women complete a job.
since how many women require to complete the job in a 40days.
10+10+10+10=40
16+16+16+16=64.
that's mean 64women complete the job in a 40days
since how many women require to complete the job in a 40days.
10+10+10+10=40
16+16+16+16=64.
that's mean 64women complete the job in a 40days
Answered by
0
4 women are required to the work in 40 days.
GIVEN
Number of women = 16
Days to complete = 10 days.
TO FIND
A number of women required to the work in 40 days.
SOLUTION
We can simply solve the above problem as follows-
We know that,
Work done = Number of days × number of women
Work done = 10 × 16. (Equation 1)
Let the number of women required to complete the work in 40 days be, x.
So,
Since work done is same, So,
x = 4
Hence, 4 women are required to the work in 40 days.
#spj2