Math, asked by ankitpathak8271, 10 months ago

a kisi kaam ko 10 din me krta hai aur b us kam ko 20 din me krta hai to dono mil kr us kaam ko kitne dino me pura krega​

Answers

Answered by yashkhandelwal230120
0

Answer:

Number of days taken by A to complete work = 10

Work done by A in a day = 1/10

Number of days taken by A to complete work = 20

Work done by A in a day = 1/20

Work done by both A and B in a day = 1/10 + 1/20

                                                             = (1 X 2)/(10 X 2) + 1/20

                                                             = 2/20 + 1/20

                                                             = 3/20

Number of days both complete the work = Total work / Work done in a day

                                                                    = 1 / 3 / 20

                                                                    = 1 X 20/3

                                                                    = 20/3 days

Hence your answer is 20/3 days.

Hope this was helpful.

Please mark me the brainliest.