A left the work 5 days before the work was completed and b left 2 days after a had left?Time and work

Answers

Answered by Anonymous
3

Step-by-step explanation:

LCM of 10,12,15 is 60

Efficiency of A = 60/10= 6

Efficiency of B = 60/12= 5

Efficiency of C = 60/15= 4

In last 3 days only C works= 3*4= 12

Before 2 Days B+C worked =2*9= 18

Remaining by A+B+C =60-30=30

30/15=2 days

Total= 5-2=7 days