a man can do a piece of work in 5 days his son help him and the work completed in 3 days in how many days his son complete the work ?
Answers
Answered by
2
Answer:
one day work of man =1/5 and let one day work of his son be 1/x.then 1/5+1/x=1/3..
x+5/5x=1/3
3x+15=5x
2x=15
x=7.5 days