a man can work 8 hours daily and finish the work in 12 days if he work 6 hours daily in how many days will the same work be finished​

Answers

Answered by Anonymous
4

Answer:

please mark me as brainlist

Explanation:

hope it helps you to understand

Attachments:
Answered by ranjankumar805136880
9

Answer:

A man works 8 hours for 12 days to complete the work.

Total number of hours reqd. to complete the work = 8*12 = 96 hours.

If he works 6 hours per day , then he may need = 96/6 = 16 days to complete his work.